  • 28th 11月 2025, Adding water to concrete onsite is not permitted

    Summary of WorkSafe Inspection – 112 Ellscott Blvd, Mickleham

    Inspectors attended site following a complaint about incorrect concrete slump causing a pump clamp failure and injury.
    No concrete works or pumps were present during the visit.
    Previous works involved pile pouring using a line pump.
    After the final pour, site management discussed slump adequacy with the pump subcontractor and instructed:

    Stop work immediately and notify management if slump concerns arise.


    Remaining piles were poured directly from agitators (no line pump used).
    Site management reported no incidents or clamp failures during line pump use.
    Internal incident register (Hammertech) showed no logged incidents.
    All pile works are now complete.
    Future slab pours will use a boom pump, with inductions reinforcing:

    Cease work and notify management if slump concerns occur.




    Recommendations
    Please note that adding water to concrete on site is not permitted under Australian Standards:


    AS 1379 – Specification and Supply of Concrete
    Clause 7.2.2: Water shall not be added after batching except as permitted and only to achieve specified slump without exceeding the maximum water–cement ratio.


    AS 3600 – Concrete Structures
    Water–cement ratio is critical for strength and durability. Increasing water beyond design mix reduces compressive strength and may result in non-compliance.


    NCC Part 3.2.3(b):
    Water must not be added to increase slump beyond specified value.


    Impact:
    Adding ~10L water per m³ can reduce 28-day compressive strength by ~2.5 MPa, compromising structural integrity.
    Correct Procedure:
    If a different slump is required, request this at the batching plant so adjustments can be made using approved admixtures, not water.

    添付ファイル :
    Designer (2).png
  • 27th 10月 2025, TOOLBOX TALK – PILING PLATFORM SAFETY & MAINTENANCE

    Purpose
    To ensure the piling platform remains safe and compliant to support the Mait HR120 piling rig during operations.
    The platform has been assessed as suitable, but only if it is maintained correctly throughout the piling works.

    Key Points
    1. Surface & Drainage
    • Platform must remain firm, level, and well-drained.
    • Maintain 1–2% slope to prevent water ponding.
    • Ensure drains and runoff paths are clear at all times.
    • Report any pooling water or soft areas immediately.

    2. After Rain or Water Exposure
    • Rain can weaken the clay subgrade and reduce bearing strength.
    • Re-inspection is mandatory after rainfall over 20 mm in 24 hours.
    • Any soft or wet zones must be:
    ○ Excavated out,
    ○ Backfilled with compacted granular material (min 8 passes), and
    ○ Rechecked before restarting piling.

    3. Surface Condition
    • Regularly inspect for ruts, settlement, or cracking caused by rig movements.
    • Any damage must be reinstated to the original thickness and re-compacted before continuing.
    • Keep the platform free of spoil, mud, or obstructions that could affect stability.

    4. Edge Protection
    • Maintain a minimum 2 m setback from all batters, trenches, pits, or vertical edges.
    • Unrestrained edges to be trimmed to a 45° slope.
    • Do not position the rig near unsupported or soft edges without engineer approval.

    5. Monitoring & Reporting
    • Conduct daily inspections and log observations.
    • Stop work immediately if any ground movement, rutting, or instability is noticed.
    • Notify the Supervisor or Geotechnical Engineer (DTM Geocivil) if distress signs are observed.

    Remember
    ✅ Safe platform = safe rig operation
    ✅ Drainage and maintenance are key
    ✅ Stop work if in doubt – inspect and confirm before continuing

    添付ファイル :
    JDTMG25-1306.Report.1- Piling Platform Report (2).pdf
  • 16th 9月 2025, Inground services as at 16.9.25

    Please review all inground services before any works

    添付ファイル :
    smaller.pdf
現場天気予報
現在の現場の天気

最終更新日時: 12:21
温度: 22C (アプリ 19C)
風速: 11KMH
最大風速: 20KMH @2:21
午前9時からの雨: 0.0mm
最低気温: 9C @6:21
最高気温: 22C @12:18
突風: 17KMH
最大突風: 26KMH @2:21


観察元 - Bureau of Meteorology
観察場所 - Melbourne Airport, VICTORIA
タイムゾーン - オーストラリア東部標準時
予測 - 月曜日, 12 1月

Partly cloudy.
: 16C マックス: 24C
降雨の可能性: 20%パーセント


予測の出典 - Bureau of Meteorology
予測場所 - Melbourne, VICTORIA
タイムゾーン - オーストラリア東部標準時
明日 - 火曜日, 13 1月

Possible shower.
: 16C マックス: 25C
降雨の可能性: 40%パーセント
予想降雨量: 0 に 2mm


重要な現場書類
現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

現場に初めてですか?

この現場のPPE要件を知っていますか?

現場での初日に備えて、適切な安全装備を確保してください。

現場のPPE要件を表示

現場に初めてですか?

現場に到着したら、すぐに作業を開始できます。

ご都合の良い時にオンラインで現場登録を完了し、時間を節約してください。

登録を開始

;